As the new year approaches, you may run into an issue where Work Center calendars need to be updated in Business Central. You will know this if you receive an error message when running MRP or scheduling a production order beginning with “Error when calculating forward. Calendar is not available after MM/DD/YY for Work Center ####”.

To address this issue, follow the below steps.

1. Navigate to the Work Centers list

Update Work Center Calendar Business Central 1

2. Click “Process”, then click “Calendar”

Update Work Center Calendar Business Central 2

3. Click “Show Matrix”. You will see that there is no capacity for dates in the new year

Update Work Center Calendar Business Central 3

4. Click “Actions” >> “Functions”>> Calculate:

Update Work Center Calendar Business Central 4

5. Choose the desired end date and work center

Update Work Center Calendar Business Central 5

6. Click “OK”.

7. Capacity for the selected work center should be updated.